Bioenergy Project FOI Documents

We have just received a significant number of documents released under FOI in relation to Mount Alexander Bioenergy’s $100,000 publicly funded Bioenergy Infrastructure Fund grant.

There is a lot of information to take in but the first thing that struck us was our description by MASG on its Permission Pathway Form to the EPA as “a small group of NIMBY protagonists”. Not a very professional look from a group that claims to highly value community relationships!

MASG even claims to have overwhelming community support including local residents (except for 4 households), the majority if not all of the Shire’s Councillors, Castlemaine Rotary (with 3 Councillors serving as Office Bearers) and Castlemaine Health. Not many conflicts of interest there!



MASG must be completely delusional, or making more false claims, if it believes its submission that only 4 households oppose the project.



The Wastewater Effluent Treatment document reveals that the site would be turned into a stinking sewage treatment plant with the addition of an industrial effluent treatment system including a huge 60m x 60m x 4m stabilising lagoon where it will be “naturally polished” for 12 months before Coliban Water will accept the discharge as trade waste.

MASG also admits that it has failed to secure a financier and is looking for Angel Investors to fund the project. That will be highly challenging given the complete lack of a social licence and multiple risks associated with the project including the prospect of legal action.

These documents are in addition to correspondence previously released in March 2022 under FOI by the Australian Government – Department of Agriculture, Fisheries and Forestry regarding Mount Alexander Bioenergy seeking approval to dispose of imported pig meat waste through its facility. This correspondence published on the Department’s disclosure log revealed that a “formal legislative approval of a proposed arrangement is not possible until the facility is built and audited for compliance with the conditions of the proposed arrangement“.

Who would invest in a project with such significant financial risks?


Don KR Planning Applications and Related Matters

The planning application by Don KR / George Weston Foods for its proposed 3.5 MW solar energy facility on zoned farmland is now under review and we are expecting it to be determined by Council at the next meeting on Tuesday 20 December 2022.

Having failed to comply with the previous Improvement Notice issued on 8 February 2022, the EPA issued a further Improvement Notice to George Weston Foods on 12 October 2022 for continuing to exceed noise limits at the factory. Council has admitted that the factory does not have a permit for night time hours of operation and is relying on 15 years existing use rights for a facility that has not existed for that length of time.


Froome’s Road Bridge

We understand that Mount Alexander Shire Council will determine the future of the Froomes Road Bridge at the next meeting on Tuesday 20 December 2022. It’s going to be a busy meeting and the Agenda containing all the recommendations is not due to be made available until 3 business days before the meeting!

This is despite refusing to release the independent consultant’s report which was provided to Council in August. We are aware however that opposition to a two-lane concrete replacement was clear in the community feedback with 85% expressing concerns.

It is also clear to us that the replacement bridge is being touted by Council in order to facilitate access by trucks potentially including B-doubles and other vehicles to the Don KR factory at Richards Road.  

Council has wilfully neglected proper maintenance of the bridge over recent years but now has the perfect opportunity to retain the heritage values of the bridge and natural character of the surrounding area and ensure the safety of local residents by restricting use to local traffic.

To that end we would also encourage you to nominate the bridge for heritage protection under Council’s current review. Suggestions for potential sites of heritage significance close on Sunday 18 December 2022.

https://www.mountalexander.vic.gov.au/Page/Page.aspx?page_Id=4439&h=0


Class Action Update

We now have a considerable amount of evidence in support of our Class Action should MASG proceed with the project.

You can still join us by emailing your contact details in confidence to:

legal@wearecrab.org

We are anticipating that this would be run on a “no win no fee” basis with no financial risk to class action group members.